Weekly works update

To keep the community informed about roads maintenance and repairs in the Cessnock Local Government Area, Council will be providing you with regular updates on where council crews are working and what they are working on.
 

In the coming week, Council teams and contractors will be working on the following roads (pending weather).
Updated for week ending: 14/04/2024

�� Orange Street, Abermain – Major works: installation of kerb and gutter and stabilised road base, continuing with drainage
�� Sandy Creek Road, Quorrobolong – Rework subgrade layer
�� New England Highway, Greta – Forming up for footpath, scheduled to pour first 80m on Friday
�� New Street, Mulbring; Gill Lane, Brunkerville; Taylors Road & Browns Road, Blackhill; Narone Creek Road, Wollombi – Grading unsealed roads
�� Ironbark Lane, Nulkaba & Old Maitland Road, Cessnock– Grading unsealed road
�� Watagan Creek Road, Laguna & Paynes Crossing Road, Wollombi – Water tabling shoulders
�� Various locations – Minor drainage works and mowing
�� Kurri Kurri – Town centre upgrade on Lang Street
�� Westcott Street, Cessnock – Bridge reconstruction State/Regional roads:
�� Buchanan Road, Lovedale Road, Hart Road, Broke Road, Wollombi Road & Great North Road – Pothole patching
�� Wollombi Road, Cessnock – Drainage maintenance
�� Wollombi Road, Millfield – Trimming overhanging trees
�� John Renshaw Drive, Blackhill – Sealing works

 

To report an issue with a road visit our online portal here.
When you lodge a customer inquiry you will be given a reference number to allow you to follow up.