Sandy Creek Road, Quorrobolong pavement rehabilitaion

  • Project typePavement Rehabilitation
  • Project value$2,140,000
  • Project scheduleLate 2022

Background

Council has committed to progressively upgrade this route, which has resulted in improved road environment and has also seen increased usage. All remaining timber bridges have been upgraded and replaced with concrete structures, removing previous load limits. Council is seeking to achieve B-Double HML access along the route from Mount Vincent to Millfield via Sandy Creek Road.

This project forms part of Council's Operational Plan. You can find it within the Operational Plan with the Project ID RRL 2021 006.

Location

Sandy Creek Road.png

Scope of works

Pavement rehab, shoulder widening, seal extensions. Existing pavement will be stabilised and resurfaced, significantly improving the current condition.

Funding

$2,140,000 including Fixing Local Roads grant and Cessnock City Council Contributions.