Camp Road, Greta

  • Project typeRoad upgrade
  • Project scheduleThe works are scheduled to commence end of January 2022 and are expected to take approximately twelve weeks to complete, weather permitting.

Council received funding under Round 7 of the Heavy Vehicle Safety and Productivity Program for the upgrade of Camp Road, Greta.

Scope of work

The construction works will include:

  • shoulder widening
  • road pavement rehabilitation
  • sealing and line-marking
  • signage 

Traffic control 

During the course of the works, unavoidable traffic disruptions will occur. Traffic control measures will be in place to minimise disruption and specific arrangements will be made for affected residents to access their properties. The Contractor will endeavour to keep residents informed of the timing and duration of the disruptions as work progresses. 

Location

The works are located at the southern end of Mansfield Street for approximately 500 metres.